ENGINEERING-PROCUREMENT-CONSTRUCTION (EPC) OF JETTY OF CIREBON 2 -CFPP 1 X 1000 MW PROJECT

PT. Dharma Subur Satya (DSS) is involved in a consortium with Hyundai Engineering  & Construction (HDEC) in the Cirebon 2-CFPP 1 x 1000 MW project. In this case, DSS is trusted to carry out on EPC of jetty 15,000 DWT capacity. Notice To Proceed (NTP)  has been made on November 9, 2017 by PT. Cirebon Energy Prasarana (CEPR). CEPR is owner of Coal Fire Power Plant (CFPP) 1 x 1000 MW Cirebon 2.
Currently, the DSS engineering team has been developing the detailed design jetty of 15,000 DWT capacity including permanent jetty, Temporary jetty, Causeway access road and Sea Water Intake. The size of jetty is trestle ( 15 m width x 2,900 m length) and Platform ( 25 m width x 165 m length ). The schedule of marine construction works shall be completed within 28 months